Do you need customer support or technical assistance? Click here to submit a support ticket...
Why critical Path is shortest project duration? 6 years 7 months ago #11616
| Hi Puneet, Yes, the critical path is the longest overall duration for the sequenced activities. It is not the shortest project duration and it is the shortest time possible to complete the project. Hope that helps. Thanks, Gail Freedman, MBA, PMP, CSM |
Why critical Path is shortest project duration? 4 years 1 month ago #20142
| Sorry, |
Why critical Path is shortest project duration? 4 years 1 month ago #20146
| Anon: Let me try: Tasks A, B, C and D all take 5 days. A must be before B and C can start. D is the final task B and C can be run in parallel after A. The Network Diagram is: A --> B/C --->D The critical path is 15 days, not 20, because B and C can be done simultaneously (Afer A) Hope that helps. Harry +++++ |
Why critical Path is shortest project duration? 4 years 1 month ago #20160
| Hi Anonymous, Take this example - Dining with friends. You all go for dinner (say 3 people). Everyone orders food and start eating... Everyone can leave only after person 3 completes his/her food. So the longest path would be reaching restaurant --> Ordering food --> Person 3 finishing the dinner --> paying bills Now lets explain float as well Hope this helps. Regards, The following user(s) said Thank You: Gabriella Dellino, PMP, Ujwala Karanam, Elizabeth Harrin, Jack Lee |
Why critical Path is shortest project duration? 3 years 5 months ago #24020
| you are a darling for that response....THANK YOU |
[emailprotected] 3 years 5 months ago #24021
| THANK YOU ANANTHA |
Why critical Path is shortest project duration? 2 years 3 weeks ago #29177
| lovely example Anantha!!! |
Why critical Path is shortest project duration? 2 years 2 weeks ago #29194
| Thank you so much. |
Moderators: Yolanda Mabutas,Mary Kathrine Padua,John Paul Bugarin,Harry Elston,Jean Kwanda,Daniel Soerensen,Elena Zelenevskaia,Christian Elmer,Christine Whitney, PMP